J.S. Held Releases Insights on Risks & Opportunities Expected to Impact Organizations in 2025
Read MoreProperty insurance for projects under construction can be significantly complex. Insuring renovation projects under a builder’s risk policy will often require more care in crafting a policy that provides adequate protection. This paper is intended to highlight the myriad complexities of insuring a renovation project under a builder’s risk policy.
To illustrate the unique issues found in insuring renovation projects, it is helpful to review the following hypothetical project.
A developer acquires a historic property in the center of a large city. The property contains a 100-year-old five-story limestone building. The developer purchased the land and building for $5 million two years prior to the anticipated construction start date and acquired zoning approvals for the renovation of the existing building, plus an addition of five floors. When completed, the project will be mixed-use office and retail. The project will include tax credits for investors.
The following are pertinent facts:
The policy will also include sub-limits for extra expense and expediting expense. In addition, the developer’s lending agreement requires delay coverage, composed of soft costs and loss of revenue. The insured also requests coverage for loss of tax credits.
The project commences as planned. Within one week after the notice to proceed, demolition activities at the interior of the historic structure have commenced. Demolition activities including use of welding equipment cause a fire which destroys the existing structure.
The complexities and potential coverage gaps created by the hypothetical fact pattern are highlighted below. Coverage problems and potential solutions are noted as follows.
Where the builder’s risk policy does not exclude coverage for existing property, the acquisition cost, representing the developer/owner’s investment in the property, is often considered. If a catastrophic loss occurred based on the hypothetical scenario, the owner would make a claim for the cost to repair or replace the property. However, in the hypothetical example, it is undisputed that such values are not included in the amount of property coverage. If, however, a catastrophic loss occurred at the end of the project, the amount of coverage would likely be insufficient to cover the cost to replace the entire project.
Potential Solutions for Issue 1
Likely the most expedient method for determining the amount of coverage is to evaluate the replacement cost value (RCV) of the existing structure and either include it as part of the building limit or as a separate sub-limit. However, this can be problematic to the extent that existing structures often have contributory economic value to a project that is less than (or at least different than) replacement cost. Thus, insuring such structures at RCV potentially creates a moral hazard.
Absent a determination of the RCV of existing structures, some policies are written subject to an existing structure’s sub-limit. This is another expedient method for dealing with such property but may not represent coverage that is sufficient if the existing property is destroyed. Such sub-limits may also exceed the economic value that the structure contributes to the completed project.
Existing structures are sometimes written at actual cash value (ACV) or may be subject to a stated sub-limit. With respect to existing structures, recognizing that the property may not have contributory market value equal to its replacement cost, ACV clauses may present significant difficulties in the adjustment of a claim. This is primarily due to a lack of jurisdictional consistency in the application of ACV. For example, if the hypothetical loss occurred in California, a state which restricts ACV to the cost of repair or replacement minus depreciation of material cost only, the ACV loss would likely be far greater than the acquisition cost. By contrast, in New York, which follows the broad evidence rule, the loss evaluation in most circumstances (If ACV was not defined in the policy) would allow consideration of the acquisition cost or market value of the structure at the time of loss. For these reasons, ACV coverage for existing property under most circumstances is not advised, unless the policy were to include a definition of ACV that limits the insurer’s obligation to an amount not to exceed the contributory economic value of the existing property at the time of loss.
Perhaps the most compelling solution to the existing structure issue would be to determine a sub-limit, or agreed amount, based on certain criteria. In this scenario, the most important question for the policyholder will be, “At what cost would repair or replacement of the existing structure become unlikely?” In the event of a catastrophic loss, an insured (and its lenders) will certainly re-evaluate the feasibility and resultant market value of the project. If the resultant value (and additional time) becomes insufficient to support the anticipated economic value at the end of the project, the developer might decide to forego the development and dispose of the property.
From an insurer’s perspective, in the event the insured chose not to repair and complete the project post-loss, then the valuation of the existing structure should arguably be the lesser of the acquisition cost of the building (segregated from the land value) or the owner’s adjusted tax basis in the existing property. The adjusted tax basis is an accounting calculation that uses the cost of an asset which is reduced by depreciation or increased by capital expenditures. To the extent that the latter method is the standard by which uninsured losses are allowed to be deducted by the Internal Revenue Service in the United States, this recognizes that reimbursement for a catastrophic loss will likely result in indemnity, i.e., the lesser of language plus demolition would make an insured whole to the extent that their investment would be protected by insurance.
The most reasonable solution could be to sub-limit existing property for its resultant contribution to the overall market value of a project at completion, but not more than its replacement cost. This information is typically available to the developer and lenders pre-construction, since it is key to understanding project feasibility. The following is an example based on the hypothetical:
If the completed project had a market value in excess of the acquisition cost of the existing structure plus construction and design costs, then the amount of the economic contribution to the completed value could be established as a sub-limit. If a project were abandoned/sold post-loss, the “lesser of” language noted herein is likely the most reasonable and equitable solution. Therefore, at the time of placement, it is important for the risk manager, broker, and underwriter to fully understand the consequences and likelihood of rebuilding in the event of a catastrophic loss to an existing structure.
A builder’s risk policy is designed to commence when construction activities begin and expire when the project is put into service for its intended use. The anticipated length of the construction project contemplated in the establishment of a policy’s start and end dates should always match the project’s schedule as determined by the general contractor or construction manager.
After a loss, the measurement of covered delay losses typically begins on the date the project would have been completed had no loss occurred and ends when the project is completed post-loss (assuming of course that there are no other non-loss related delays). The complexities associated with having to determine the period of restoration (time to repair or replace) and its impact on the date of completion require a significant level of study. The following are just some of the many questions that must be answered:
The above questions and others give rise to a complex set of issues that should be studied and given consideration prior to the issuance of a policy. On one hand, the developer and lenders will be seeking coverage, in most instances, for the potential losses that might occur from catastrophic damages presented in the hypothetical. On the other hand, underwriters may be unwilling to take on the risk of the uncertainties presented in the hypothetical.
Potential Solutions for Issue 2
From the standpoint of a policyholder (and additional insureds such as lenders), decisions regarding what actions will be taken to continue with the project as planned will almost always be driven by the feasibility of the post-loss project. Proper diligence will require new feasibility and market analyses showing the potentially changed post-loss economic assumptions. A decision to “re-imagine” and execute the project will be driven by profitability and the resultant post completion market value of the project.
If existing property has contributory market value less than its replacement cost, it is incumbent upon the risk manager, the broker, and the underwriter to understand the potential ramifications of a catastrophic loss.
Time element coverages should be crafted with a view toward the potential gaps in coverage that may be created by a delay period that exceeds the anticipated project schedule at the time of binding. Recognition of the following can reduce coverage ambiguities post-loss:
Builder’s risk policies and time element coverages for renovation projects can be more complex than new construction projects. The myriad factors created by each unique renovation project require exceptional care, outside-the-box thinking, and carefully tailored language to insure an appropriate level of protection. Risk managers, brokers, and underwriters need to be mindful of these early on in the process in order to avoid confusion and contention following a loss.
Disclaimer: We at J.S. Held do not interpret, underwrite, or place policies. The intent of this article is to offer our expertise regarding complex situations such as those hypothetically described within.
We would like to thank Jonathon Held, CEO, for providing insights and expertise that greatly assisted this research.
Jonathon C. Held is the CEO of J.S. Held, LLC, a global consulting firm with more than 1500 multidisciplinary professionals. During his career, Mr. Held has provided consulting services to clients on large builder’s risk projects and losses. He has acted as an expert witness and dispute resolution panelist in numerous cases. He has also lectured and written extensively on the subject of builder’s risk insurance and claims. Mr. Held is a founding executive committee member of the Builder’s Risk & Construction Symposium, an educational program that brings together diverse global stakeholders in builder’s risk insurance in an annual symposium designed to educate and promote collaboration.
Jon can be reached at [email protected].
While there are some similarities between Builder’s Risk and Property Damage claims, there are also numerous differences in the way they are managed and evaluated. Some questions that often arise when a claim occurs on...
Measuring delay from a loss under a builder’s risk insurance policy is perhaps the most complicated of all time element measures in the claims world. Setting aside the numerous complex issues of coverage, builders risk...
Read real-life builder's risk claim case studies, uncover the pivotal roles of key players, & gain insights into risk management processes that safeguard project continuity and financial stability....